Pennington County Highway Department has developed a
long-range
Transportation Improvement Plan. |
 |
- Rochford Road
The Pennington County Board of Commissioners have selected HDR Engineering, Inc. out of Rapid City, SD to
complete an Environmental Impact Statement for the reconstruction of Rochford Road from Rochford South to
Deerfield Road. HDR Engineering, Inc. will be developing a website for the project as well as seeking public
comments in the near future. Once the website is developed and available, we will post a link to it here.
|
- Reservoir & Long View Road
This project is substantially complete. Final asphalt surfacing on the project is complete. Two-way traffic
has been restored on Reservoir Road and permanent pavement marking is complete. Limited amounts of sidewalk
and ADA ramps still remain and are scheduled to be completed in the spring of 2011. Final surface restoration
as well as sod placement are also scheduled for the spring of 2011.
|
- Sheridan Lake Road
The reconstruction of Sheridan Lake Road from Alberta Drive to State Highway 385 is under design by Ferber
Engineering. Preliminary plans have been completed. The South Dakota Department of Transportation is
developing an Environmental Assessment for the project. Upon completion of the Environmental Assessment,
a public meeting to review the plans and accept comments will be scheduled.
|
 |
-
Asphalt overlay on Spring Creek Road from Arena Drive to State Highway 79,
estimated cost $222,000.
-
Asphalt overlay on 173rd Avenue from Interstate 90 to the county line,
estimated cost $262,000.
-
Chip seal approximately 29 miles of various county roads throughout the county,
estimated cost $550,000.
-
Crush and produce 120,000 tons of gravel and 1,000 tons of rip rap for various
county roads, estimated cost $414,000.
|
|
| |
 |
|